Under construction
ASTER
MahaRERA P52100007322High risk
Survey Number 11/6, Pisoli, 411028
Post your property hereOwn or renting out a unit in ASTER? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Pisoli come to you.
Dec 2017
Possession
45.5%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Dec 2017) has passed with construction at 45.5%.
Satellite view of this address
Where it is · Survey Number 11/6, Pisoli
Promoter
Builder profile
KALAPI VENTURES
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52100007322
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2017
- Construction
- 45.5% complete
- Units sold
- 0 of 0
Similar projects in Pisoli
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Prime Vista
PisoliPoss. December 2029
EMERALD GREEN
PisoliPoss. August 2028
Prime Vista Row Houses
PisoliPoss. December 2029
Advika Phase IV-C
PisoliPoss. December 2030
GAGAN LAWISH PHASE 2
Pisoli100% builtPoss. December 2020
ARV Imperia C, D and E Building
Pisoli100% builtPoss. December 201828 complaints
ATUR VALLY VISTA WING B
Pisoli95% builtPoss. December 2017
BROOKEFIELD WILLOWS
Pisoli90.9% builtPoss. December 20191 complaint
Keep exploring
Where this project sits, who built it, and how Pisoli compares.
In Pisoli
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.