High risk
  • Possession delayed ~2 yrs. Originally promised Jul 2024, now proposed Jul 2026 per the RERA filing.
  • Possession date passed. The proposed possession date (Jul 2026) has passed with construction at 81.8%.
Satellite view of this address

Where it is · 31, DRONAGIRI

Area guide

What it's like to buy in DRONAGIRI

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
KALPANA STERLING INFRA LLP

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
AMIT N PATIL ARCHITECTS

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52000022340
Status
New
Stage
Certificate Signed
Possession
July 2026originally July 2024
Construction
81.8% complete
Units sold
10 of 52

Similar projects in DRONAGIRI

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how DRONAGIRI compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.