🏗️
Under construction

ATLANTA RESIDENCY PHASE II

MahaRERA P51700010106High risk

by SRI BALAJI DEVELOPER

124/5/6/7/9/10, 125/8/10, 159/6. 161/5/8/14, Bhiwandi, 421302

Official record
Apr 2027
Possession
47.3%
Built
1
Complaints
143
Units
High risk
  • Possession delayed ~7 yrs. Originally promised Dec 2019, now proposed Apr 2027 per the RERA filing.
  • Behind schedule. Possession is due Apr 2027 but construction is only at 47.3%.
Satellite view of this address

Where it is · 124/5/6/7/9/10, 125/8/10, 159/6. 161/5/8/14, Bhiwandi

Area guide

What it's like to buy in Bhiwandi

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
SRI BALAJI DEVELOPER

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Navrachna

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P51700010106
Status
Ongoing
Stage
Certificate Signed
Possession
April 2027originally December 2019
Construction
47.3% complete
Units sold
99 of 143

Similar projects in Bhiwandi

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Bhiwandi compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.