High risk
  • Possession delayed ~3 yrs. Originally promised Oct 2019, now proposed Sept 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Sept 2022) has passed with construction at 80%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2022 per the RERA filing.
Satellite view of this address

Where it is · 1466A, Borivali

Promoter

Builder profile

Builder
NAMOREALTY AND INFRA LLP

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51800011731
Status
Ongoing
Stage
Certificate Signed
Possession
September 2022originally October 2019
Construction
80% complete
Units sold
0 of 0

Similar projects in Borivali

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Borivali compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.