High risk
  • Litigation pending (2). MahaRERA's litigation disclosure lists 2 pending cases against this project.
  • Mortgaged to a lender (₹100 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹100 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
  • Possession delayed ~3 yrs. Originally promised Jun 2024, now proposed Oct 2027 per the RERA filing.
  • High complaint rate. 4 complaints against only 1 sold units — a high rate for a project this size.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Oct 2027 per the RERA filing.

Area guide

What it's like to buy in Borivali

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
S D CORPORATION PRIVATE LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51800025637
Status
New
Stage
Certificate Signed
Possession
October 2027originally June 2024
Construction
41.5% complete
Units sold
1 of 1

Similar projects in Borivali

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Borivali compares.

Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.