Under construction

AUDUMBAR DARSHAN

MahaRERA P51700033432High risk

by AUDUMBAR ENTERPRISES

SURVEY NO 55 H NO 3/A/10 PLOT NO 2, BADLAPUR EAST, 421503

Official record
Oct 2024
Possession
44.5%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Oct 2024) has passed with construction at 44.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2024 per the RERA filing.
Satellite view of this address

Where it is · SURVEY NO 55 H NO 3/A/10 PLOT NO 2, BADLAPUR EAST

Area guide

What it's like to buy in BADLAPUR EAST

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
AUDUMBAR ENTERPRISES

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
MAHAN DEDHIA

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P51700033432
Status
New
Stage
Certificate Signed
Possession
October 2024originally January 2024
Construction
44.5% complete
Units sold
0 of 0

Similar projects in BADLAPUR EAST

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how BADLAPUR EAST compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.