High risk
  • 1 appeal at MahaREAT. 1 complaint against this project has been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~2 yrs. Originally promised Oct 2024, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Satellite view of this address

Where it is · P-KK-8-25, Thane

Promoter

Builder profile

Builder
ASAYA BUILDERS AND DEVELOPERS LLP

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
Hiten Sethi & Associates

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51700018167
Status
New
Stage
Certificate Signed
Possession
December 2026originally October 2024
Construction
67.3% complete
Units sold
76 of 85

Similar projects in Thane

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Thane compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.