AVANT HILLWAY
by RAGHVENDRA CONSTRUCTION COMPANY PVT LTD
CTS NO 610 A/1B/1, m, 400063
- 2 appeals at MahaREAT. 2 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
- Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Apr 2027 per the RERA filing.
- 16 RERA complaints. 16 complaint records are disclosed against this project on MahaRERA.
- Behind schedule. Possession is due Apr 2027 but construction is only at 27.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2027 per the RERA filing.
Where it is · CTS NO 610 A/1B/1, m
Area guide
What it's like to buy in m
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Film City flank with large integrated townships on both flanks.
- Growth drivers:
- Oberoi/NESCO belt, Metro 7, Western Express Highway offices.
- Who buys here:
- Upgraders wanting township amenities without Powai prices.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P51800010785
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- April 2027originally December 2024
- Construction
- 27.5% complete
- Units sold
- 97 of 185