High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2018, now proposed Oct 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Oct 2020) has passed with construction at 35%.
Satellite view of this address

Where it is · 110/11/2, Baner

Promoter

Builder profile

Builder
Avenue Buildcon

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100002633
Status
Ongoing
Stage
Certificate Signed
Possession
October 2020originally December 2018
Construction
35% complete
Units sold
0 of 0

Similar projects in Baner

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Baner compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.