Under construction

Avenue Park - I

MahaRERA P51800005425High risk

by CB Enterprises

590, 590/1 to 6, 591, 592, 592/1 t o 12, 593, 593/1 to 2, 594,594/1 to 37, pathanwadi, 400097

Official record
Sept 2024
Possession
73.5%
Built
1
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Jun 2022, now proposed Sept 2024 per the RERA filing.
  • Possession date passed. The proposed possession date (Sept 2024) has passed with construction at 73.5%.
Satellite view of this address

Where it is · 590, 590/1 to 6, 591, 592, 592/1 t o 12, 593, 593/1 to 2, 594,594/1 to 37, pathanwadi

Area guide

What it's like to buy in pathanwadi

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Andheri WestUpper-mid

Entertainment-industry heartland — dense, lively, well connected.

Growth drivers:
Metro lines 1/2A, Lokhandwala–Versova redevelopment wave.
Who buys here:
Media professionals, first upgraders, rental investors.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
CB Enterprises

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51800005425
Status
Ongoing
Stage
Certificate Signed
Possession
September 2024originally June 2022
Construction
73.5% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how pathanwadi compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.