High risk
  • Litigation pending (2). MahaRERA's litigation disclosure lists 2 pending cases against this project.
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 0%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2025 per the RERA filing.
Satellite view of this address

Where it is · CTS NO.1320 A PT/1320/A/21/1 TO 4, 1320/A/22 TO 33, Mulund East, Opp Navghar Police Station, MHADA Colony, Mulund East,

Area guide

What it's like to buy in Mulund East

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Tata Housing Development Company Limited

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
KAPADIA ASSOCIATES DESIGN LLP

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51900007740
Status
Ongoing
Stage
Certificate Signed
Possession
December 2025
Construction
0% complete
Units sold
0 of 296

Keep exploring

Where this project sits, who built it, and how Mulund East, Opp Navghar Police Station, MHADA Colony, Mulund East, compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.