Under construction

BALAJI KRUPA

MahaRERA P52100022955High risk

by SANTOSH DINKAR NARVEKAR

PLOT NO. 78, GAT NO. 457 AND OTHERS, Mulshi, 412115

Official record
Jul 2026
Possession
73.1%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Jun 2022, now proposed Jul 2026 per the RERA filing.
  • Possession date passed. The proposed possession date (Jul 2026) has passed with construction at 73.1%.

Promoter

Builder profile

Builder
SANTOSH DINKAR NARVEKAR

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100022955
Status
New
Stage
Certificate Signed
Possession
July 2026originally June 2022
Construction
73.1% complete
Units sold
0 of 0

Similar projects in Mulshi

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Mulshi compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.