🏗️
Under construction

BANDRA NORTH GULMOHAR AVENUE

MahaRERA P51800014036High risk

by SHIVALIK VENTURES PRIVATE LIMITED

CTS NO 30/326-328,30/334-335,30/341,30/343-416,30/529,30/531,30/533-534,30/547-551,30/581-789, Andheri, 400051

Official record
Dec 2026
Possession
73.9%
Built
37
Complaints
741
Units
High risk
  • 8 appeals at MahaREAT. 8 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~3 yrs. Originally promised Aug 2023, now proposed Dec 2026 per the RERA filing.
  • 37 RERA complaints. 37 complaint records are disclosed against this project on MahaRERA.
  • Promised amenities not started. Gymnasium, Landscaped Garden, Kids Play Area are at 0% build with possession due Dec 2026 per the RERA filing.
Satellite view of this address

Where it is · CTS NO 30/326-328,30/334-335,30/341,30/343-416,30/529,30/531,30/533-534,30/547-551,30/581-789, Andheri

Area guide

What it's like to buy in Andheri

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Santacruz / KharUltra-luxury

Bandra's quieter northern neighbour — low-rise lanes going boutique.

Growth drivers:
Society redevelopment, airport and BKC equidistance.
Who buys here:
Professionals wanting Bandra adjacency with less noise.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
SHIVALIK VENTURES PRIVATE LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51800014036
Status
New
Stage
Certificate Signed
Possession
December 2026originally August 2023
Construction
73.9% complete
Units sold
461 of 741

Similar projects in Andheri

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Andheri compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.