Caution
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Promoter
Builder profile
Bappa Developers
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52100029777
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026
- Construction
- 50.9% complete
- Units sold
- 0 of 0
Similar projects in MAAN
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Menlo Estella
MAANPoss. December 20283 complaints
Tinsel Town Phase I
MAAN100% builtPoss. December 20191 complaint
SAI SIDDHI APARTMENT
MAAN82.7% builtPoss. December 2026
SPORTSVILLE PHASE 1
MAAN47.3% builtPoss. December 2027
Kohinoor Central Park - Phase II
MAAN7.7% builtPoss. October 2029
Keep exploring
Where this project sits, who built it, and how MAAN compares.
In MAAN
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.