Bellanza Phase 2 - Wing D, E, F at The Prestige City
by PRESTIGE MULUND REALTY PRIVATE LIMITED
19/5 (Part), Kurla, 400080
- Litigation pending (34). MahaRERA's litigation disclosure lists 34 pending cases against this project.
- Behind schedule. Possession is due Jun 2027 but construction is only at 5.5%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Jun 2027 per the RERA filing.
Where it is · 19/5 (Part), Kurla
Area guide
What it's like to buy in Kurla
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Leafy eastern-suburb favourite with big redevelopment supply.
- Growth drivers:
- Eastern Express Highway, proposed Goregaon–Mulund link, mall belt.
- Who buys here:
- Eastern-suburb families upgrading within the area.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51800046488
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2027
- Construction
- 5.5% complete
- Units sold
- 758 of 799
Similar projects in Kurla
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Kurla compares.
In Kurla
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.