High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 37.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Promoter

Builder profile

Builder
Mohd Khalid Mohd Iqbal Shaikh

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Horizon Consultancy

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52000054829
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
37.3% complete
Units sold
0 of 38