Under construction

Bhagyoday Residency Wing B

MahaRERA P52100001551High risk

by K C B Builders

Survey No 97/1A/1A/1A/2, Pimpri Chinchawad (M Corp.), 412101

Official record
Dec 2021
Possession
50%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2019, now proposed Dec 2021 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 50%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2021 per the RERA filing.
Satellite view of this address

Where it is · Survey No 97/1A/1A/1A/2, Pimpri Chinchawad (M Corp.)

Promoter

Builder profile

Builder
K C B Builders

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100001551
Status
Ongoing
Stage
Certificate Signed
Possession
December 2021originally December 2019
Construction
50% complete
Units sold
0 of 0

Similar projects in Pimpri Chinchawad (M Corp.)

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Pimpri Chinchawad (M Corp.) compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.