BHAMA AMBER
S.NO-4671,4672,4673,4674,7848, NEAR OLD POLICE STATION, 410506
- Possession delayed ~5 yrs. Originally promised Jun 2023, now proposed Jul 2028 per the RERA filing.
Where it is · S.NO-4671,4672,4673,4674,7848, NEAR OLD POLICE STATION
Area guide
What it's like to buy in NEAR OLD POLICE STATION
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52100020046
- Status
- New
- Stage
- Certificate Signed
- Possession
- July 2028originally June 2023
- Construction
- 63.6% complete
- Units sold
- 12 of 33
Keep exploring
Where this project sits, who built it, and how NEAR OLD POLICE STATION compares.
In NEAR OLD POLICE STATION
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.