Bhandup Citizen CHS Ltd
424 B, Bhandup W, 400078
- Litigation pending (4). MahaRERA's litigation disclosure lists 4 pending cases against this project.
- Possession delayed ~7 yrs. Originally promised Jun 2021, now proposed Mar 2028 per the RERA filing.
Where it is · 424 B, Bhandup W
Area guide
What it's like to buy in Bhandup W
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Central crossroads reborn via freeway and Metro links.
- Growth drivers:
- Eastern Freeway, Monorail/Metro, BKC proximity at half the price.
- Who buys here:
- BKC-bound professionals and long-time Chembur families.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P51800015109
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2028originally June 2021
- Construction
- 56.4% complete
- Units sold
- 0 of 78
Keep exploring
Where this project sits, who built it, and how Bhandup W compares.
In Bhandup W
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 11 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.