High risk
- Possession delayed ~8 yrs. Originally promised Aug 2019, now proposed Mar 2027 per the RERA filing.
- Behind schedule. Possession is due Mar 2027 but construction is only at 47.3%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.
Satellite view of this address
Where it is · 72/167, 0
Area guide
What it's like to buy in 0
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
Pankaj Chauhan
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P99000013206
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2027originally August 2019
- Construction
- 47.3% complete
- Units sold
- 34 of 47
Similar projects in 0
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
VIJAY HOMES
070.9% builtPoss. March 2027
VASTU ARCADE
058.6% builtPoss. December 2021
RUIKAR PLAZA
014.1% builtPoss. October 2022
Keep exploring
Where this project sits, who built it, and how 0 compares.
In 0
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.