High risk
  • 7 appeals at MahaREAT. 7 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • 9 RERA complaints. 9 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 59.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2023 per the RERA filing.
Satellite view of this address

Where it is · 99/4, Badlapur (M Cl)

Area guide

What it's like to buy in Badlapur (M Cl)

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Ambernath / BadlapurValue

The value frontier beyond Kalyan — low-rise affordability, improving rail links.

Growth drivers:
Extended suburban rail, industrial-belt employment, lowest entry prices in MMR.
Who buys here:
First-home buyers stretching every rupee.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Kalyani Enterprises

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51800003594
Status
Ongoing
Stage
Certificate Signed
Possession
December 2023
Construction
59.1% complete
Units sold
0 of 0

Similar projects in Badlapur (M Cl)

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Badlapur (M Cl) compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.