🏗️
Under construction

Bhaveshwar Nagar Building No. 3

MahaRERA P51800003355High risk

by Yog Reality

Final Plot No. 25, CTS No. 5953, Kurla, 400077

Official record
Mar 2022
Possession
99.5%
Built
1
Complaints
0
Units
High risk
  • Litigation pending (3). MahaRERA's litigation disclosure lists 3 pending cases against this project.
  • Possession delayed ~3 yrs. Originally promised Mar 2019, now proposed Mar 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Mar 2022) has passed with construction at 99.5%.
Satellite view of this address

Where it is · Final Plot No. 25, CTS No. 5953, Kurla

Area guide

What it's like to buy in Kurla

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Ghatkopar / VikhroliUpper-mid

Metro-1 anchor with Godrej's Vikhroli land bank next door.

Growth drivers:
Metro 1 interchange, Eastern Express Highway, corporate campuses.
Who buys here:
Families wanting east-side connectivity to BKC/Fort.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Yog Reality

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51800003355
Status
Ongoing
Stage
Certificate Signed
Possession
March 2022originally March 2019
Construction
99.5% complete
Units sold
0 of 0

Similar projects in Kurla

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Kurla compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.