Under construction

BHOOMI CLASSIC BUILDING NO. 2

MahaRERA P99000004505High risk

by APNA SAI BUILDERS AND DEVELOPERS

S NO. 143, S NO. 145 H NO. 2, S NO. 161 H NO 1PLUS2/7, Vasai, 401203

Official record
Apr 2027
Possession
45.5%
Built
0
Complaints
0
Units
High risk
  • Behind schedule. Possession is due Apr 2027 but construction is only at 45.5%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Apr 2027 per the RERA filing.
Satellite view of this address

Where it is · S NO. 143, S NO. 145 H NO. 2, S NO. 161 H NO 1PLUS2/7, Vasai

Promoter

Builder profile

Builder
APNA SAI BUILDERS AND DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P99000004505
Status
Ongoing
Stage
Certificate Signed
Possession
April 2027originally December 2026
Construction
45.5% complete
Units sold
0 of 0

Similar projects in Vasai

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Vasai compares.

Data sourced from the official MahaRERA portal; complaints last synced 24 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.