Under construction

BLDG NO-1 M.BARIA EVEREST

MahaRERA P99000004326High risk

by MORESHWAR KRUSHNA BARIA

S NO-35 HISSA NO 8 AND S NO 36 HISSA NO 1-9, Vasai, 401303

Official record
Mar 2022
Possession
90.9%
Built
5
Complaints
0
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Dec 2017, now proposed Mar 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Mar 2022) has passed with construction at 90.9%.
Satellite view of this address

Where it is · S NO-35 HISSA NO 8 AND S NO 36 HISSA NO 1-9, Vasai

Area guide

What it's like to buy in Vasai

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
MORESHWAR KRUSHNA BARIA

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P99000004326
Status
Ongoing
Stage
Certificate Signed
Possession
March 2022originally December 2017
Construction
90.9% complete
Units sold
0 of 0

Similar projects in Vasai

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Vasai compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.