Under construction

BLDG NO-9 M.BARIA TWIN TOWER

MahaRERA P99000003970High risk

by M/s MAGNATES ENTERPRISES

S. NO 423, HISSA NO A3 AND A4, Vasai, 401303

Official record
Nov 2020
Possession
98.2%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~3 yrs. Originally promised May 2018, now proposed Nov 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Nov 2020) has passed with construction at 98.2%.
Satellite view of this address

Where it is · S. NO 423, HISSA NO A3 AND A4, Vasai

Promoter

Builder profile

Builder
M/s MAGNATES ENTERPRISES

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P99000003970
Status
Ongoing
Stage
Certificate Signed
Possession
November 2020originally May 2018
Construction
98.2% complete
Units sold
0 of 0

Similar projects in Vasai

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Vasai compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.