High risk
  • Behind schedule. Possession is due Apr 2027 but construction is only at 28.2%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Apr 2027 per the RERA filing.

Area guide

What it's like to buy in CHARHOLI BK

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Ganesh Satish Patil

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100053136
Status
New
Stage
Certificate Signed
Possession
April 2027originally December 2026
Construction
28.2% complete
Units sold
0 of 0

Similar projects in CHARHOLI BK

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how CHARHOLI BK compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.