Under construction
BLUE BAY
MahaRERA P52000005297High risk
by SONDE BUILDERS & DEVELOPERS PRIVATE LIMITED
SURVEY NO-30, PLOT NO-13, 14, 18, 19, 20, Karjat, 410201
Post your property hereOwn or renting out a unit in BLUE BAY? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Karjat come to you.
Dec 2026
Possession
63%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~9 yrs. Originally promised Jan 2018, now proposed Dec 2026 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Satellite view of this address
Where it is · SURVEY NO-30, PLOT NO-13, 14, 18, 19, 20, Karjat
Promoter
Builder profile
SONDE BUILDERS & DEVELOPERS PRIVATE LIMITED
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52000005297
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2026originally January 2018
- Construction
- 63% complete
- Units sold
- 0 of 0
Similar projects in Karjat
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Eshaanya Phase 1
KarjatPoss. December 2025
RIVERGATE ARANYA
KarjatPoss. December 2022
Sanskruti Plots, Phase III
KarjatPoss. December 2018
Sierra View
KarjatPoss. December 2021
BHIMASHANKAR HILLS
KarjatPoss. December 20181 complaint
Kalpataru Aria - Phase A
KarjatPoss. March 20251 complaint
Meraki Phase 2
KarjatPoss. April 2027
Kalpataru Aria - Phase C
KarjatPoss. December 2025
Keep exploring
Where this project sits, who built it, and how Karjat compares.
In Karjat
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.