Under construction
Blue Dice
MahaRERA P52100004228High risk
Gat No 1593 , 1596 , 1597/1 ,1597/2, Chikhali Bk., 411062
Post your property hereOwn or renting out a unit in Blue Dice? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Chikhali Bk. come to you.
Jan 2022
Possession
72.7%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~2 yrs. Originally promised Jan 2020, now proposed Jan 2022 per the RERA filing.
- Possession date passed. The proposed possession date (Jan 2022) has passed with construction at 72.7%.
- Promised amenities not started. Clubhouse is at 0% build with possession due Jan 2022 per the RERA filing.
Satellite view of this address
Where it is · Gat No 1593 , 1596 , 1597/1 ,1597/2, Chikhali Bk.
Promoter
Builder profile
DHANRAJ KESARIMAL SONIGARA
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100004228
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- January 2022originally January 2020
- Construction
- 72.7% complete
- Units sold
- 0 of 0
Similar projects in Chikhali Bk
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
STKANWARRAMPALACIOPHASE1
Chikhali Bk.90.9% builtPoss. December 2019
AKSHA VRUNDAVAN
Chikhali Bk.90.9% builtPoss. December 2018
Casa RIO Phase I
Chikhali Bk.90.9% builtPoss. July 2018
NEELKANTH RESIDENCY
Chikhali Bk.56.4% builtPoss. June 2019
Keep exploring
Where this project sits, who built it, and how Chikhali Bk. compares.
In Chikhali Bk.
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.