Borivli Vasundhara CHS Ltd.
by Shree Sai Shraddha Developers
290/4-B, Borivali East, 400066
- Possession delayed ~6 yrs. Originally promised Jan 2020, now proposed Dec 2025 per the RERA filing.
- Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 72.7%.
Where it is · 290/4-B, Borivali East
Area guide
What it's like to buy in Borivali East
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Film City flank with large integrated townships on both flanks.
- Growth drivers:
- Oberoi/NESCO belt, Metro 7, Western Express Highway offices.
- Who buys here:
- Upgraders wanting township amenities without Powai prices.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51800006294
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2025originally January 2020
- Construction
- 72.7% complete
- Units sold
- 0 of 0
Similar projects in Borivali East
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Borivali East compares.
In Borivali East
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.