Under construction

BROOKLYN PARK PHASE IV

MahaRERA P99000000417High risk

by EKTA HOUSING PRIVATE LIMITED

66/169 PT, 68/171 PT, 69/172, , Vasai, 401303

Official record
Dec 2026
Possession
68.9%
Built
54
Complaints
189
Units
High risk
  • 13 appeals at MahaREAT. 13 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~6 yrs. Originally promised Jan 2021, now proposed Dec 2026 per the RERA filing.
  • 54 RERA complaints. 54 complaint records are disclosed against this project on MahaRERA.
Satellite view of this address

Where it is · 66/169 PT, 68/171 PT, 69/172, , Vasai

Area guide

What it's like to buy in Vasai

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
EKTA HOUSING PRIVATE LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Samir Desai

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P99000000417
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally January 2021
Construction
68.9% complete
Units sold
116 of 189

Similar projects in Vasai

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Vasai compares.

Data sourced from the official MahaRERA portal; complaints last synced 21 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.