High risk
  • Possession delayed ~1 yr. Originally promised Jan 2021, now proposed Jun 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2022) has passed with construction at 63.6%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2022 per the RERA filing.
Satellite view of this address

Where it is · CTS NO 1B-1-B, Borivali

Promoter

Builder profile

Builder
C H PATIL AND SONS LLP

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51800003936
Status
Ongoing
Stage
Certificate Signed
Possession
June 2022originally January 2021
Construction
63.6% complete
Units sold
0 of 0

Similar projects in Borivali

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.