  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 54.4%.
Satellite view of this address

Where it is · Plot R-3/1 part, Hinjwadi Ph-3

Area guide

What it's like to buy in Hinjwadi Ph-3

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Hinjawadi Infradevelelopment Private Limited

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100013714
Status
New
Stage
Certificate Signed
Possession
December 2023
Construction
54.4% complete