Under construction

BUSINESS PLUS

MahaRERA P51600024000High risk

by MANGO ESTTATE

SURVEY No. 588/2, FINAL PLOT No. 115/P, CTS No. 7256, NEAR HOTEL SANDIP NASHIK, 422001

Official record
Dec 2026
Possession
90.2%
Built
0
Complaints
182
Units
High risk
  • Possession delayed ~1 yr. Originally promised Sept 2025, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Satellite view of this address

Where it is · SURVEY No. 588/2, FINAL PLOT No. 115/P, CTS No. 7256, NEAR HOTEL SANDIP NASHIK

Promoter

Builder profile

Builder
MANGO ESTTATE

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
SUMIT M KUMATH M KUMATH

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P51600024000
Status
New
Stage
Certificate Signed
Possession
December 2026originally September 2025
Construction
90.2% complete
Units sold
103 of 182

Keep exploring

Where this project sits, who built it, and how NEAR HOTEL SANDIP NASHIK compares.

Data sourced from the official MahaRERA portal; complaints last synced 24 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.