Under construction

CASTLE PEAK

MahaRERA P51800007470High risk

by INNERSPACE

PLOT NO. 142 CTS NO. 190, 190/1, Kurla, 400071

Official record
Mar 2019
Possession
69.1%
Built
4
Complaints
0
Units
High risk
  • Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
  • 2 appeals at MahaREAT. 2 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession date passed. The proposed possession date (Mar 2019) has passed with construction at 69.1%.
Satellite view of this address

Where it is · PLOT NO. 142 CTS NO. 190, 190/1, Kurla

Area guide

What it's like to buy in Kurla

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Kurla / ChemburMid-income

Central crossroads reborn via freeway and Metro links.

Growth drivers:
Eastern Freeway, Monorail/Metro, BKC proximity at half the price.
Who buys here:
BKC-bound professionals and long-time Chembur families.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
INNERSPACE

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51800007470
Status
Ongoing
Stage
Certificate Signed
Possession
March 2019originally March 2018
Construction
69.1% complete
Units sold
0 of 0

Similar projects in Kurla

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Kurla compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.