High risk
  • Possession date passed. The proposed possession date (Jun 2019) has passed with construction at 36.2%.

Promoter

Builder profile

Builder
Arena Constructions

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100017006
Status
New
Stage
Certificate Signed
Possession
June 2019
Construction
36.2% complete
Units sold
0 of 0