CHARMS CITY PHASE II
164/2, Titwala, 421605
- Possession delayed ~5 yrs. Originally promised Jul 2022, now proposed Mar 2027 per the RERA filing.
Where it is · 164/2, Titwala
Area guide
What it's like to buy in Titwala
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P51700005462
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2027originally July 2022
- Construction
- 87.7% complete
- Units sold
- 125 of 189
Similar projects in Titwala
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Titwala compares.
In Titwala
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 21 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.