Caution
  • Possession delayed ~2 yrs. Originally promised Dec 2026, now proposed Dec 2028 per the RERA filing.
Satellite view of this address

Where it is · 36/6, Village Bhadav

Area guide

What it's like to buy in Village Bhadav

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
ATMARAM NARAYAN SHINDE

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
AR MANASI MAYEKAR

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P52000056422
Status
New
Stage
Certificate Signed
Possession
December 2028originally December 2026
Construction
40% complete
Units sold
10 of 85

Keep exploring

Where this project sits, who built it, and how Village Bhadav compares.

Data sourced from the official MahaRERA portal; complaints last synced 25 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.