All RERA projects
🏗️
Under construction

Chintamani Heights (Building No 1) & Chintamani Kuber (Building No 2)

MahaRERA P51700030843High risk

by Chintamani Developers

358 (Old) 5 (New) Hissa No 7, 16(PT)& 18, Devichapada, 421202

Official record
Apr 2027
Possession
80.3%
Built
0
Complaints
90
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Apr 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2027 per the RERA filing.
Satellite view of this address

Where it is · 358 (Old) 5 (New) Hissa No 7, 16(PT)& 18, Devichapada

Promoter

Builder profile

Builder
Chintamani Developers

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
Decon Associates

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P51700030843
Status
New
Stage
Certificate Signed
Possession
April 2027originally December 2023
Construction
80.3% complete
Units sold
25 of 90