Under construction
CITY ICON WING A
MahaRERA P52100028263High risk
343/A SHANIWAR PETH, SHANIWAR PETH, 411030
Post your property hereOwn or renting out a unit in CITY ICON WING A? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in SHANIWAR PETH come to you.
May 2024
Possession
50.2%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (May 2024) has passed with construction at 50.2%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due May 2024 per the RERA filing.
Promoter
Builder profile
A AND D CONSTRUCTIONS
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52100028263
- Status
- New
- Stage
- Certificate Signed
- Possession
- May 2024
- Construction
- 50.2% complete
- Units sold
- 0 of 0
Similar projects in SHANIWAR PETH
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
YASHORATNA APARTMENT
SHANIWAR PETH90.9% builtPoss. May 2026
YASHODHAN PHASE 1 BUILDING B
SHANIWAR PETH90.9% builtPoss. December 2022
SUMANGAL PRIDE
SHANIWAR PETH81.4% builtPoss. April 2022
YASHOGANDHARV
SHANIWAR PETH80% builtPoss. July 2025
JAGANNATH PATIL TOWER
SHANIWAR PETH60% builtPoss. December 2027
ANAND VIHAR RESIDENCY
SHANIWAR PETH47.7% builtPoss. December 2028
GULAB KUNJ
SHANIWAR PETH41.4% builtPoss. December 2019
VATSALYA VIHAR
SHANIWAR PETH27.3% builtPoss. September 2020
Keep exploring
Where this project sits, who built it, and how SHANIWAR PETH compares.
In SHANIWAR PETH
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.