🏗️
Under construction
Clover Casablanca Phase II
MahaRERA P52100002277Caution
by Worthwhile Properties Pvt. Ltd.
91/1, 91/2, Mawal, 412106
Post your property hereOwn or renting out a unit in Clover Casablanca Phase II? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Mawal come to you.
Dec 2019
Possession
90.9%
Built
0
Complaints
0
Units
Caution
- Possession date passed. The proposed possession date (Dec 2019) has passed with construction at 90.9%.
Satellite view of this address
Where it is · 91/1, 91/2, Mawal
Promoter
Builder profile
Worthwhile Properties Pvt. Ltd.
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52100002277
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2019originally December 2018
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Similar projects in Mawal
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Vaarivana Phase D - 2A
MawalPoss. February 2027
Vaarivana Phase D - 2B
MawalPoss. August 20271 complaint
Riverland Ph 2
MawalPoss. April 2029
Riverland Ph 1
MawalPoss. April 2029
Urbanbrick Castle Phase 2
MawalPoss. December 2028
GREENDALE ENA
MawalPoss. April 2027
RIVERLAND PH-4
MawalPoss. April 2029
RIVERLAND PH-5
MawalPoss. April 2029
Keep exploring
Where this project sits, who built it, and how Mawal compares.
In Mawal
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.