Post your property hereOwn or renting out a unit in Constructing EWS and LIG Tenements under PMAY on S No 86 95 and 133 at Shirdhon Tal Kalyan DistThane? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Kalyan come to you.
Jul 2027
Possession
16.3%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~5 yrs. Originally promised Mar 2022, now proposed Jul 2027 per the RERA filing.
- Behind schedule. Possession is due Jul 2027 but construction is only at 16.3%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2027 per the RERA filing.
Area guide
What it's like to buy in Kalyan
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
MAHARASHTRA HOUSING AND AREA DEVELOPMENT AUTHORITY
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51700016820
- Status
- New
- Stage
- Certificate Signed
- Possession
- July 2027originally March 2022
- Construction
- 16.3% complete
- Units sold
- 0 of 0
Similar projects in Kalyan
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
RITZ LIFE TOWER J
KalyanPoss. April 2029
RITZ EUROPA TOWER A
KalyanPoss. April 2031
SANTOSSHI AVENUE
KalyanPoss. April 2032
Mangeshi Crown
KalyanPoss. July 2032
Chanakya C wing
KalyanPoss. February 2030
Chanakya A wing
KalyanPoss. April 2028
BARKU HORIZON
KalyanPoss. December 2030
LAXMI PRATIMA HEIGHTS
KalyanPoss. April 2028
Keep exploring
Where this project sits, who built it, and how Kalyan compares.
In Kalyan
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 16 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.