All RERA projects
🏗️
Under construction

Construction of 83 LIG Ts on Guest plot CTS no 43 Pt of Unnatagar, Village Pahadi goregaon

MahaRERA P51800000023High risk

by MUMBAI HOUSING AND AREA DEVELOPMENT BOARD

43 , Andheri, 400062

Official record
Oct 2020
Possession
90.9%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2018, now proposed Oct 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Oct 2020) has passed with construction at 90.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2020 per the RERA filing.
Satellite view of this address

Where it is · 43 , Andheri

Area guide

What it's like to buy in Andheri

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

GoregaonUpper-mid

Film City flank with large integrated townships on both flanks.

Growth drivers:
Oberoi/NESCO belt, Metro 7, Western Express Highway offices.
Who buys here:
Upgraders wanting township amenities without Powai prices.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
MUMBAI HOUSING AND AREA DEVELOPMENT BOARD

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51800000023
Status
Ongoing
Stage
Certificate Signed
Possession
October 2020originally December 2018
Construction
90.9% complete
Units sold
0 of 0

Similar projects in Andheri

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Andheri compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.