Under construction

CRYSTAL APARTMENT

MahaRERA P52000053146High risk

by JAVED ISLAM KHAN

CTS NO 1648 S NO 62 H NO 8+9 PLOT NO 5 AND 6, CHINCHAVALI SHEKIN, 410203

Official record
Oct 2027
Possession
44.5%
Built
0
Complaints
0
Units
High risk
  • Behind schedule. Possession is due Oct 2027 but construction is only at 44.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2027 per the RERA filing.
Satellite view of this address

Where it is · CTS NO 1648 S NO 62 H NO 8+9 PLOT NO 5 AND 6, CHINCHAVALI SHEKIN

Promoter

Builder profile

Builder
JAVED ISLAM KHAN

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52000053146
Status
New
Stage
Certificate Signed
Possession
October 2027originally June 2027
Construction
44.5% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how CHINCHAVALI SHEKIN compares.

Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.