High risk
  • Possession date passed. The proposed possession date (Feb 2023) has passed with construction at 31.4%.
Satellite view of this address

Where it is · 59/5, MOHOMMADWADI

Promoter

Builder profile

Builder
TRIMURTI DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100019837
Status
New
Stage
Certificate Signed
Possession
February 2023
Construction
31.4% complete
Units sold
0 of 0