Caution
  • Possession date passed. The proposed possession date (Oct 2025) has passed with construction at 90.9%.

Promoter

Builder profile

Builder
DAIWIK-AAKAR INFRADEV LLP

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51800048431
Status
New
Stage
Certificate Signed
Possession
October 2025
Construction
90.9% complete
Units sold
0 of 0

Similar projects in GOREGAON EAST

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how GOREGAON EAST compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.