Under construction

DATTA SAMARTH

MahaRERA P51700050343High risk

by PANDURANG ARJUN CHAWAN

SURVEY NO. 1277, 1278/A, 1279/A, 1280/A, 1281/A, 1282/A, 1283, 1284 AND 1285/A, Thane, 400603

Official record
Jun 2026
Possession
77%
Built
0
Complaints
19
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Jun 2024, now proposed Jun 2026 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 77%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2026 per the RERA filing.
Satellite view of this address

Where it is · SURVEY NO. 1277, 1278/A, 1279/A, 1280/A, 1281/A, 1282/A, 1283, 1284 AND 1285/A, Thane

Area guide

What it's like to buy in Thane

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
PANDURANG ARJUN CHAWAN

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
JITESH P. PAWAR & ASSOCIATES

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51700050343
Status
New
Stage
Certificate Signed
Possession
June 2026originally June 2024
Construction
77% complete
Units sold
2 of 19

Similar projects in Thane

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Thane compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.