Under construction

DATTACHHAYA

MahaRERA P99000054805High risk

by JAGDISH MANOHAR MHATRE

PLOT NO.1- S.N.379/A/B/2, S.N.531-PLOT NO.2&3, VIRAR WEST, 401303

Official record
Mar 2027
Possession
42%
Built
0
Complaints
168
Units
High risk
  • Litigation pending (2). MahaRERA's litigation disclosure lists 2 pending cases against this project.
  • Possession delayed ~1 yr. Originally promised Sept 2025, now proposed Mar 2027 per the RERA filing.
  • Behind schedule. Possession is due Mar 2027 but construction is only at 42%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.
Satellite view of this address

Where it is · PLOT NO.1- S.N.379/A/B/2, S.N.531-PLOT NO.2&3, VIRAR WEST

Area guide

What it's like to buy in VIRAR WEST

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
JAGDISH MANOHAR MHATRE

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
SANAT MEHTA

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P99000054805
Status
New
Stage
Certificate Signed
Possession
March 2027originally September 2025
Construction
42% complete
Units sold
52 of 168

Similar projects in VIRAR WEST

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how VIRAR WEST compares.

Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.