DB Commercial Phase II
by Pune Buildtech Private Limited
SNO 191A/2A/1/2, Plot 3B C, Yerawada, 411006
- Possession delayed ~2 yrs. Originally promised Dec 2019, now proposed Dec 2021 per the RERA filing.
- Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 60.9%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2021 per the RERA filing.
Where it is · SNO 191A/2A/1/2, Plot 3B C, Yerawada
Area guide
What it's like to buy in Yerawada
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
The western line's volume market — dense affordable towers past Mira Road.
- Growth drivers:
- Suburban rail quadrupling, coastal-road extensions, MMR's biggest affordable pipeline.
- Who buys here:
- Budget-first buyers who commute the western line.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P52100003455
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2021originally December 2019
- Construction
- 60.9% complete
- Units sold
- 0 of 0
Similar projects in Yerawada
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Yerawada compares.
In Yerawada
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.