High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2019, now proposed Dec 2021 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 60.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2021 per the RERA filing.
Satellite view of this address

Where it is · SNO 191A/2A/1/2, Plot 3B C, Yerawada

Area guide

What it's like to buy in Yerawada

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Vasai–VirarValue

The western line's volume market — dense affordable towers past Mira Road.

Growth drivers:
Suburban rail quadrupling, coastal-road extensions, MMR's biggest affordable pipeline.
Who buys here:
Budget-first buyers who commute the western line.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Pune Buildtech Private Limited

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Ankur Associates

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100003455
Status
Ongoing
Stage
Certificate Signed
Possession
December 2021originally December 2019
Construction
60.9% complete
Units sold
0 of 0

Similar projects in Yerawada

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.