High risk
  • Possession delayed ~1 yr. Originally promised Dec 2025, now proposed Apr 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2027 per the RERA filing.
Satellite view of this address

Where it is · Survey No 79 Hissa No 3, At Village - Kharvai, Badlapur

Promoter

Builder profile

Builder
M/s. Deepali Infracon LLP

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Raj Associates

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51700048280
Status
New
Stage
Certificate Signed
Possession
April 2027originally December 2025
Construction
80.9% complete
Units sold
4 of 112