High risk
  • Behind schedule. Possession is due Apr 2027 but construction is only at 39.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2027 per the RERA filing.
Satellite view of this address

Where it is · Plot No -38 ,Sector No-3, Pushpak - Dapoli

Promoter

Builder profile

Builder
Lakshdeep Developer LLP

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52000052328
Status
New
Stage
Certificate Signed
Possession
April 2027originally December 2026
Construction
39.5% complete
Units sold
7 of 113